Facility capacity testing at the time a project is expected to reach design capacity. The timing in which this takes place varies by type of facility. Acceptance testing may occur shortly after start-up of a process unit, 6 to 12 months on building or mechanical trains, or 2 to 3 years for a paper mill.
Addition (Add-on)- A new addition that ties in to an existing facility, often intended to expand capacity. Synonym: Expansion.
Alliance PartnerA participant in a long-term association with a non-affiliated organization, used to further the common interests of the members. The continued association is based upon mutual trust and the satisfactory performance of each participant, and the alliance as a whole, rather than a pure contractual obligation.
Automation/Integration (AI) TechnologyThe Automation and Integration Technology practice addresses the degree of automation/level of use and integration of automated systems for predefined tasks/work functions common to most projects.
The use of automatic identification technology by labeling, identifying, and controlling items, materials, and equipment through the use of bar codes. A bar code can be defined as a self contained message with information encoded in the widths of bars and spaces in a printed pattern.
A change is any event that results in a modification of the project work, schedule or cost. Owners and designers frequently initiate changes during design development to reflect changes in project scope or preferences for equipment and materials other than those originally specified. Contractors often initiate changes when interferences are encountered, when designs are found to be not constructable, or other design errors are found.
Change ManagementChange Management is the process of incorporating a balanced change culture of recognition, planning and evaluation of project changes in an organization to effectively manage project changes.
ConstructabilityConstructability is the effective and timely integration of construction knowledge into the conceptual planning, design, construction and field operations of a project to achieve the overall project objectives in the best possible time and accuracy, at the most cost-effective levels. Contingency. All costs in contingency accounts including but not limited to normal contingency, allowances, reserves, indirect costs for schedule contingency, escalation, etc.
Cost of LandThe cost of land includes the purchase price of the land obtained for project use. It does not include the cost of preparing the land for use, such as soil remediation, demolition of existing structures, site preparation, etc.
Cost of Quality ManagementThe sum of those costs associated with quality deviation prevention and appraisal activities. Examples include:
Computer aided drafting system that provides three-dimensional views for checking physical interferences in addition to providing two and three dimensional drafting capabilities.
The sum of those costs associated with actual performance of tasks involved in rework. Examples include:
EDI is a technology that permits the direct computer-to-computer exchange of data in a standard format. Data is transmitted in a standard industry format, checked for error, and imported directly into the receiving computer system without re-keying.
Expansion- A new addition that ties in to an existing facility, often intended to expand capacity. Synonym: Addition.
A new facility from the foundations and up. A project requiring demolition of an existing facility before new construction begins is also classified as grass roots.
An integrated database is a concept of organizing, storing, and managing all electronic data relating to a project in such a fashion that data is entered and stored once and then accessed and utilized by multiple users and applications. The users may include those involved with facility planning, design, procurement, construction, plant operations, and suppliers.
Materials management is an integrated process for planning and controlling all necessary efforts to make certain that the quality and quantity of materials and equipment are appropriately specified in a timely manner, are obtained at a reasonable cost, and are available when needed. The materials management systems combine and integrate the takeoff, vendor evaluation, purchasing, expediting, warehousing, distribution, and disposing of materials functions.
Mechanical CompletionThe point in time when a plant is capable of being operated although some trim, insulation, and painting may still be needed. This occurs after completion of precommissioning. In some industries, mechanical completion may have the same general meaning as beneficial occupancy.
ModernizationA facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Renovation, Upgrade.
ModularizationModularization refers to the use of offsite construction. For the purposes of the benchmarking data, modularization includes all work that represents substantial offsite construction and assembly of components and areas of the finished project. Examples that would fall within this categorization include:
Modularization does not include offsite fabrication of components. Examples of work that would be excluded from the definition of modularization include:
Startup is the transitional phase between plant construction completion and commercial operations, including all of the activities that bridge these two phases. Planning for Startup consists of a sequence of activities that begins during requirements definition and extends through initial operations.
Pre-Project PlanningPre-Project Planning involves the process of developing sufficient strategic information that owners can address risk and decide to commit resources to maximize the chance for a successful project. Pre-project planning includes putting together the project team, selecting technology, selecting project site, developing project scope, and developing project alternatives. Pre-project planning is often perceived as synonymous with front-end loading, front-end planning, feasibility analysis, and conceptual planning. Project Budget at Authorization to Proceed. This is the estimated cost for your company’s portion of the project at authorization to proceed. If your contract had cost changes before authorization to proceed, then these changes should be included in the project budget. Do not include estimated costs for change orders received during project execution.
Project Development ChangesChanges required to execute the original scope of work or obtain original process basis. Examples include:
Practices related to the management and control of both scope changes and project changes. P&IDs (Piping and Instrumentation Diagrams). Schematic diagrams which show the layout and relationship of piping and instrumentation.
P&IDs (Piping and Instrumentation Diagrams)Schematic diagrams which show the layout and relationship of piping and instrumentation.
Quality Management incorporates all activities conducted to improve the efficiency, contract compliance and cost effectiveness of design, engineering, procurement, QA/QC, construction, and start-up elements of construction projects.
A facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Modernization, Upgrade.
Changes in the base scope of work or process basis. Examples include:
Team Building is a project-focused process that builds and develops shared goals, interdependence, trust and commitment, and accountability among team members and that seeks to improve team members problem-solving skills.
Total Actual Project CostThis is the total actual cost of all work performed by your company, including costs attributable to work added or deducted by change orders.
Turnaround/Shutdown/OutageThe period during which a boiler, generating unit, transmission line, or other facility is shutdown and unable to perform its normal operations. The shutdown of a facility including for maintenance, inspection, testing, regulatory changes, or, in some cases, for refuelling is known as a planned shutdown. Turnaround is interchangeable with shutdown or outage depending on industry groups.
A facility for which a substantial amount of the equipment, structure, or other components is replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms: Modernization, Renovation.
Zero accident techniques include the site specific safety programs and implementation, auditing and incentive efforts to create a project environment and a level of training that embraces the mind set that all accidents are preventable and that zero accidents is an obtainable goal.